17042 W BOLLINGER DR 90272
Certificate Information: 17042 W BOLLINGER DR 90272
- Application / Permit
- 20047-20000-01362
- Plan Check / Job No.
- B20VN11019
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" X 28'-0" SWIMMING POOL AND 6'-0" X 6'-0" SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #270.
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Current Status
- Issued on 9/18/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/31/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/17/2020 | JENNIFER LEE |
| Issued | 9/18/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/31/2020 | JEROME MAGAT PALMA |
| Construction near power lines | Cleared | 9/4/2020 | WALTER RAMIREZ |
| Coastal Zone | Cleared | 9/9/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 9/9/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 9/9/2020 | LAUREN PADICK |
| ZA Case | Cleared | 9/9/2020 | LAUREN PADICK |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 1/8/2021 | Approved | ANDREW NAVE |
| Pre-Gunite | 1/8/2021 | Conditional Approval | ANDREW NAVE |
| Rough-Plumbing | 1/8/2021 | Approved | ANDREW NAVE |
| Deck | 6/14/2021 | Approved | ANDREW NAVE |
| Enclosure/Fence | 9/24/2021 | Approved | ANDREW NAVE |
| Pool Equipment Noise Test | 10/28/2021 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Approved | ANDREW NAVE |
| Final | 11/9/2021 | Corrections Issued | ANDREW NAVE |
| Pre-Gunite | 11/9/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Not Ready | ANDREW NAVE |