700 E BROOKS AVE 90291
Certificate Information: 700 E BROOKS AVE 90291
- Application / Permit
- 20047-20000-01360
- Plan Check / Job No.
- B20VN11013
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15'-8" X 8'-10" SWIMMING POOL PER STANDARD PLAN #268 AND ENGINEER DETAILS.
- Permit Issued
- Issued on 3/11/2021
- Issuing Office
- Current Status
- CofO Issued on 11/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 9/21/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/2/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 10/30/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 12/11/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 3/5/2021 | ROSENDO MEDINA |
| Plan Check Approved | 3/9/2021 | ROSENDO MEDINA |
| Issued | 3/11/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| CofO in Progress | 10/7/2021 | JOHNNY MIRANDA |
| Permit Finaled | 11/15/2021 | DANIEL ORRANTE |
| CofO Issued | 11/15/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/15/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/15/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/15/2020 | MIGUEL GAMBOA |
| Coastal Zone | Cleared | 2/9/2021 | JASON CHAN |
| Miscellaneous | Cleared | 2/9/2021 | JASON CHAN |
| Miscellaneous | Cleared | 2/9/2021 | JASON CHAN |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 13437 VENTURA BLVD #216 SHERMAN OAKS, CA 91423 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 3/24/2021 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 4/29/2021 | Approved | JOHNNY MIRANDA |
| Pre-Gunite | 4/29/2021 | Approved | JOHNNY MIRANDA |
| Deputy Shotcrete | 4/30/2021 | No Access for Inspection | DAVID HEINE |
| Gas Piping or Gas Test | 5/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Deck | 5/25/2021 | Not Ready for Inspection | PIERRE VEGA |
| Grounding or Bonding | 5/25/2021 | Corrections Issued | PIERRE VEGA |
| Enclosure/Fence | 5/26/2021 | Corrections Issued | JOHNNY MIRANDA |
| Deck | 6/2/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Enclosure/Fence | 6/2/2021 | Corrections Issued | JOHNNY MIRANDA |
| Deck | 6/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 6/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Enclosure/Fence | 6/4/2021 | Approved | JOHNNY MIRANDA |
| Grounding or Bonding | 6/4/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 6/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 7/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 10/5/2021 | Partial Approval | JOHNNY MIRANDA |