2240 S PATRICIA AVE 90064
Certificate Information: 2240 S PATRICIA AVE 90064
- Application / Permit
- 20047-20000-01337
- Plan Check / Job No.
- B20VN10918
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADD A NEW 6' X 8' SPA INSIDE (E) POOL AND RAISE POOL DEPTH FROM 7'-6" TO 4'-6" PER STANDARD PLAN #268
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 8/27/2020 | RAPHAEL ROSAS |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 9/23/2021 | CARLOS MATAMOROS |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Brite Pool Plastering; Lic. No.: 976733-C53 | 13413 CORCORAN STREET SAN FERNANDO, CA 91340 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2020 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 9/25/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 10/14/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 12/18/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 2/3/2021 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 2/17/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/31/2021 | Corrections Issued | MATT KELLERMAN |
| Pool Equipment Noise Test | 4/7/2021 | Approved | ROBERT CHAVEZ |
| Final | 4/14/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/21/2021 | Approved | CARLOS MATAMOROS |
| Final | 9/21/2021 | Partial Approval | CARLOS MATAMOROS |