3443 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 3443 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 20047-20000-01318
- Plan Check / Job No.
- B20VN10793
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 31' SWIMMING POOL WITH ATTACHED 7' X 6' SPA AND POOL VAULT COVER PER LA CITY STANDARD PLAN #270
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 8/25/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/4/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 11/9/2021 | OMAR GARNICA |
| Plan Check Approved | 1/10/2022 | OMAR GARNICA |
| Issued | 1/11/2022 | APPLICANT |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| CofO in Progress | 3/28/2023 | KEVIN SARGSYAN |
| Permit Finaled | 4/11/2023 | DANIEL ORRANTE |
| CofO Issued | 4/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Watercourse | Cleared | 12/17/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 3/7/2022 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 3/7/2022 | Conditional Approval | JUAN VALENZUELA |
| Deck | 3/15/2022 | Corrections Issued | MICHAEL PELHAM |
| Pre-Gunite | 3/15/2022 | Approved | MICHAEL PELHAM |
| Deputy Shotcrete | 3/24/2022 | Conditional Approval | JUAN VALENZUELA |
| Deck | 6/3/2022 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 7/14/2022 | Corrections Issued | JUAN VALENZUELA |
| Enclosure/Fence | 7/28/2022 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Corrections Issued | JUAN VALENZUELA |
| Final | 10/11/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Approved | KEVIN SARGSYAN |
| Final | 3/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| Equipment Noise Level | 3/16/2023 | Approved | JAMES VORHIS |
| Final | 3/23/2023 | OK to Issue CofO | KEVIN SARGSYAN |