2106 N BARRYWOOD AVE 90731
Certificate Information: 2106 N BARRYWOOD AVE 90731
- Application / Permit
- 20047-20000-01316
- Plan Check / Job No.
- B20VN10787
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 36'-0" X 16'-0" SWIMMING POOL AND 8'-0" X 8'-0" SPA PER STANDARD PLAN #268.
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 7/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/23/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/14/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/17/2020 | JEROME MAGAT PALMA |
| Issued | 9/17/2020 | APPLICANT |
| CofO in Progress | 7/12/2021 | ANSON MAGLASANG |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
| CofO Issued | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/21/2020 | JEROME MAGAT PALMA |
| ZA Case | Cleared | 9/14/2020 | STEVEN WECHSLER |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-C53 | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/27/2020 | Approved | JOHN KLARIN |
| Gas Piping or Gas Test | 10/27/2020 | Approved | JOHN KLARIN |
| Pool Piping | 10/27/2020 | Approved | JOHN KLARIN |
| Pre-Gunite | 10/27/2020 | Approved | JOHN KLARIN |
| Rough-Electrical | 10/27/2020 | Partial Inspection | JOHN KLARIN |
| Rough-Plumbing | 10/27/2020 | Approved | JOHN KLARIN |
| Deputy Shotcrete | 10/30/2020 | Approved | JOHN KLARIN |
| Deck | 11/30/2020 | Corrections Issued | JOHN KLARIN |
| Grounding or Bonding | 11/30/2020 | Approved | JOHN KLARIN |
| Enclosure/Fence | 12/2/2020 | Not Ready for Inspection | JOHN KLARIN |
| Enclosure/Fence | 12/14/2020 | Not Ready for Inspection | JOHN KLARIN |
| Enclosure/Fence | 12/18/2020 | Not Ready for Inspection | JOHN KLARIN |
| Enclosure/Fence | 3/31/2021 | Approved | JOHN KLARIN |
| Rough-Electrical | 3/31/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 5/24/2021 | Approved | JOHN KLARIN |
| Final | 5/24/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 5/24/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Approved | JOHN KLARIN |
| Final | 6/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| Grounding or Bonding | 6/4/2021 | Approved | JOHN KLARIN |
| Equipment Noise Level | 6/8/2021 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 7/7/2021 | OK to Issue CofO | JOHN KLARIN |