2311 W SCOTT AVE 90026
Certificate Information: 2311 W SCOTT AVE 90026
- Application / Permit
- 20047-20000-01219
- Plan Check / Job No.
- B20VN10141
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17'-0" X 27'-0" SWIMMING POOL AND 8'-0" X 9'-0" SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 5/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/17/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/2/2020 | LUIS RINCON |
| Plan Check Approved | 11/9/2020 | LUIS RINCON |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 5/7/2021 | ROBERT VORHIS |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
| CofO Issued | 5/19/2021 | DEROLD HAUFF |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/17/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/15/2021 | Corrections Issued | SCOTT FINNILA |
| Pre-Gunite | 2/1/2021 | Corrections Issued | OSVALDO PARAMO |
| Pre-Gunite | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Deck | 3/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Enclosure/Fence | 3/23/2021 | Approved | KATHRYN BUTTERWORTH |
| Grounding or Bonding | 4/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 4/21/2021 | Corrections Issued | ROBERT VORHIS |
| Pool Equipment Noise Test | 4/21/2021 | Approved | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 5/3/2021 | Approved | ROBERT VORHIS |
| Final | 5/3/2021 | Conditional Approval | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2021 | SGSOV Approved | ROBERT VORHIS |