3235 N BERRY DR 91604

Certificate Information: 3235 N BERRY DR 91604

Application / Permit
20047-20000-01201
Plan Check / Job No.
B20VN10063
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ADD 9' X 9' SPA INSIDE (E) POOL PER ENGINEERING
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 RAPHAEL ROSAS
Corrections Issued 8/13/2020 RAPHAEL ROSAS
Applicant returned to address corrections 2/8/2021 RAPHAEL ROSAS
Applicant returned to address corrections 3/6/2021 RAPHAEL ROSAS
Plan Check Approved 3/24/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/5/2021 APPLICANT
Issued 4/19/2021 APPLICANT
CofO in Progress 6/30/2022 CHRISTOPHE COCHRAN
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 9/9/2020 VINCENT QUITORIANO
Eng Process Fee Ord 176,300 Cleared 9/14/2020 JOHN TRIANTAFYLLOS
ZI Cleared 12/3/2020 DOMINICK ORTIZ
Miscellaneous Cleared 1/21/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 4/28/2021 Off-Hour Fees Due
Pool Piping 4/28/2021 Off-Hour Fees Due
Pre-Gunite 4/28/2021 Off-Hour Fees Due
Rough-Electrical 4/28/2021 Off-Hour Fees Due
Rough-Plumbing 4/28/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 5/1/2021 Partial Approval CHARLES POWELL
Gas Piping or Gas Test 5/1/2021 Approved CHARLES POWELL
Pre-Gunite 5/1/2021 Approved CHARLES POWELL
Rough-Plumbing 5/1/2021 Approved CHARLES POWELL
Deputy Shotcrete 5/7/2021 Conditional Approval ARAM AVEDISIAN
Grounding or Bonding 5/20/2021 Approved ARAM AVEDISIAN
Grounding or Bonding 5/20/2021 Off-Hour Fees Due
Enclosure/Fence 8/30/2021 Approved ARAM AVEDISIAN
Equipment Noise Level 6/14/2022 Approved FELIPE PENICHE
Final 6/17/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 6/30/2022 OK to Issue CofO CHRISTOPHE COCHRAN