10550 W DRAPER AVE 90064
Certificate Information: 10550 W DRAPER AVE 90064
- Application / Permit
- 20047-20000-01152
- Plan Check / Job No.
- B20VN09757
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 10' X 31 POOL AND 6' X 6' SPA. POOL COVER PROVIDED.
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 1/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | GEORGE ALVAREZ |
| Corrections Issued | 8/19/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 10/19/2020 | MANUEL GARCIA |
| Plan Check Approved | 11/25/2020 | MOHAMMAD ESMAILI |
| Issued | 11/25/2020 | APPLICANT |
| CofO in Progress | 12/29/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/6/2023 | DANIEL ORRANTE |
| CofO Issued | 1/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/19/2020 | GEORGE ALVAREZ |
| Grading Pre-Inspection | Cleared | 8/19/2020 | GEORGE ALVAREZ |
| Construction near power lines | Cleared | 11/23/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Signature Pools And Landscapes; Lic. No.: 537939-C53 | 18017 CHATSWORTH ST SUITE 677 GRANADA HILLS, CA 91344 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/1/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Gunite | 4/6/2021 | Conditional Approval | KEVIN SARGSYAN |
| Grounding or Bonding | 8/18/2021 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 8/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 8/3/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 12/6/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 12/9/2022 | Approved | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Approved | OGANES TARAKHCHYAN |
| Pre-Gunite | 12/13/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 12/28/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Approved | OGANES TARAKHCHYAN |