1060 N ACANTO PL 90049
Certificate Information: 1060 N ACANTO PL 90049
- Application / Permit
- 20047-20000-01120
- Plan Check / Job No.
- B20VN09544
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16'-0" X 32'-0" SWIMMING POOL AND 6'-0" X 6'-0" SPA WITHIN PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- Issued on 7/30/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/28/2020 | JEROME MAGAT PALMA |
| Issued | 7/30/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/28/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/3/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 9/16/2020 | Approved | CARLOS MATAMOROS |
| Pool Piping | 9/16/2020 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 9/16/2020 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 11/12/2020 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 11/12/2020 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 11/14/2020 | Partial Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Approved | CARLOS MATAMOROS |
| Final | 11/17/2020 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 11/18/2020 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 11/20/2020 | Approved | CARLOS MATAMOROS |
| Final | 11/20/2020 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 11/25/2020 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/25/2020 | SGSOV Approved | EVAN COOPER |
| Final | 7/28/2023 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 6/18/2024 | Corrections Issued | STUART CHAPMAN |