3004 N ACRESITE ST 90039

Certificate Information: 3004 N ACRESITE ST 90039

Application / Permit
20047-20000-01104
Plan Check / Job No.
B20VN09395
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 15'-0" X 24'-0" SWIMMING POOL AND 7'-0" X 5'-0" SPA WITHIN PER STANDARD PLAN $268 AND ENGINEER DETAIL
Permit Issued
Issued on 7/29/2020
Issuing Office
Current Status
CofO Issued on 6/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/21/2020 JEROME MAGAT PALMA
Corrections Issued 7/22/2020 JEROME MAGAT PALMA
Plan Check Approved 7/23/2020 JEROME MAGAT PALMA
Issued 7/29/2020 APPLICANT
CofO in Progress 5/1/2021 DAVID FEILER
Permit Finaled 6/7/2021 DEROLD HAUFF
CofO Issued 6/7/2021 DEROLD HAUFF
Permit Finaled 6/7/2021 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Fidelity Builders & Design Inc; Lic. No.: 1022172-B 617 S OLIVE ST STE 1007      LOS ANGELES, CA 90014
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Grounding or Bonding 9/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Gunite 9/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 9/22/2020 Corrections Issued HAMIK HARTOUNIAN
Rough-Electrical 9/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Plumbing 9/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/22/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/2/2020 Approved HAMIK HARTOUNIAN
Pre-Gunite 10/2/2020 Approved HAMIK HARTOUNIAN
Pre-Inspection 10/2/2020 Approved HAMIK HARTOUNIAN
Rough-Electrical 10/2/2020 Approved HAMIK HARTOUNIAN
Rough-Plumbing 10/2/2020 Partial Approval HAMIK HARTOUNIAN
Deck 1/21/2021 Approved HAMIK HARTOUNIAN
Enclosure/Fence 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Equipment Noise Level 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pool Equipment Noise Test 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/21/2021 SGSOV Not Ready HAMIK HARTOUNIAN
ELECTRICAL-Final 2/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/1/2021 Corrections Issued HAMIK HARTOUNIAN
Gas Piping or Gas Test 2/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 2/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Special/Order Compliance 2/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Enclosure/Fence 2/5/2021 Approved HAMIK HARTOUNIAN
Pool Equipment Noise Test 3/18/2021 Approved DA LIU
Final 3/19/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved HAMIK HARTOUNIAN
Final 4/30/2021 OK to Issue CofO DAVID FEILER