1635 N CASALE ROAD 90272
Certificate Information: 1635 N CASALE ROAD 90272
- Application / Permit
- 20047-20000-01087
- Plan Check / Job No.
- B20VN09240
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 36'X8' SWIMMING POOL W/ 9'5"X6' SPA PER STD. PLAN #270 & ENGR DETAILS SEE COMMENTS.
- Permit Issued
- Issued on 12/3/2020
- Issuing Office
- Current Status
- CofO Issued on 11/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 7/21/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/18/2020 | HAYATO TSUCHIYA |
| Issued | 12/3/2020 | APPLICANT |
| CofO in Progress | 11/15/2022 | JUAN VALENZUELA |
| Permit Finaled | 11/18/2022 | DANIEL ORRANTE |
| CofO Issued | 11/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/29/2020 | KIRK LINKLATER |
| Low Impact Development | Cleared | 9/29/2020 | MARTIN FRAGOSO |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Borgese Rocco Pasquale; Lic. No.: 852378-B | 739 10TH STREET, UNIT B SANTA MONICA, CA 90402 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 1/22/2021 | Approved | MATT KELLERMAN |
| Pool Piping | 1/22/2021 | Approved | MATT KELLERMAN |
| Pre-Gunite | 1/22/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Rough-Electrical | 1/22/2021 | Approved | MATT KELLERMAN |
| Rough-Plumbing | 1/22/2021 | Approved | MATT KELLERMAN |
| Pre-Gunite | 2/4/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 8/3/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 8/3/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Enclosure/Fence | 8/13/2021 | Approved | JOHN KIDWELL |
| Pool/Spa Cover | 8/13/2021 | Approved | JOHN KIDWELL |
| Pool Equipment Noise Test | 8/31/2021 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/28/2021 | Approved | JUAN VALENZUELA |
| Final | 10/28/2021 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/28/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Equipment Noise Level | 10/28/2022 | Approved | JAMES VORHIS |
| Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/7/2022 | Approved | JUAN VALENZUELA |
| Final | 11/7/2022 | Conditional Approval | JUAN VALENZUELA |