15461 W DE PAUW ST 90272

Certificate Information: 15461 W DE PAUW ST 90272

Application / Permit
20047-20000-01080
Plan Check / Job No.
B20VN09201
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED 14' X 34' POOL AND 8' X 8' SPA PER STANDARD PLAN #268
Permit Issued
Issued on 11/14/2020
Issuing Office
Current Status
CofO Issued on 3/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 RAPHAEL ROSAS
Corrections Issued 7/18/2020 RAPHAEL ROSAS
Applicant returned to address corrections 10/5/2020 RAPHAEL ROSAS
Applicant returned to address corrections 10/20/2020 RAPHAEL ROSAS
Issued 11/14/2020 APPLICANT
CofO in Progress 3/4/2022 ANDREW NAVE
Permit Finaled 3/7/2022 DANIEL ORRANTE
CofO Issued 3/7/2022 DANIEL ORRANTE
Permit Finaled 3/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 7/24/2020 LAUREN PADICK
Coastal Zone Cleared 9/17/2020 PABLO ESTRADA
ZI Cleared 9/17/2020 PABLO ESTRADA
Grading Pre-Inspection Cleared 10/5/2020 RAPHAEL ROSAS

Contact Information

Contractor Infinity Pool Service; Lic. No.: 891370-C53 9121 ATLANTA AVE PMB #638      HUNTINGTON BEACH, CA 92646
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1499 IRIS GROVE DR      CORONA, CA 92881

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 2/23/2021 Partial Approval ANDREW NAVE
Pool Piping 2/23/2021 Approved ANDREW NAVE
Pre-Gunite 2/23/2021 Conditional Approval ANDREW NAVE
Deputy Shotcrete 2/25/2021 Conditional Approval ANDREW NAVE
Gas Piping or Gas Test 3/24/2021 Partial Inspection ANDREW NAVE
Enclosure/Fence 8/5/2021 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 8/5/2021 Approved ANDREW NAVE
Grounding or Bonding 8/5/2021 Corrections Issued ANDREW NAVE
Enclosure/Fence 8/9/2021 Approved ANDREW NAVE
Grounding or Bonding 8/9/2021 Approved ANDREW NAVE
Final 10/4/2021 Corrections Issued ANDREW NAVE
Pool Equipment Noise Test 10/4/2021 Approved JAMES VORHIS
Pool/Spa Cover 10/4/2021 Approved ANDREW NAVE
Pre-Gunite 10/4/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Not Ready ANDREW NAVE
Gas Piping or Gas Test 10/28/2021 Approved ANDREW NAVE
Final 2/17/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Approved ANDREW NAVE
Final 3/4/2022 Conditional Approval ANDREW NAVE