10033 W ROSSBURY PL 90064
Certificate Information: 10033 W ROSSBURY PL 90064
- Application / Permit
- 20047-20000-01070
- Plan Check / Job No.
- B20VN09159
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15'-6" X 32'-8" SWIMMING POOL AND 7'-0" X 6'-0" SPA WITHIN PER STANDARD PLAN #268
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/18/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 8/20/2020 | OMAR GARNICA |
| Plan Check Approved | 11/5/2020 | OMAR GARNICA |
| Issued | 11/5/2020 | APPLICANT |
| CofO in Progress | 5/8/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
| CofO Issued | 6/11/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/18/2020 | JEROME MAGAT PALMA |
| Specific Plan | Cleared | 8/18/2020 | PABLO ESTRADA |
| Construction near power lines | Cleared | 10/19/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Coastal Aquatic Creations; Lic. No.: 697943-C53 | 149 SOUTH BARRINGTON AVE #158 LOS ANGELES, CA 90049 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2022 | Approved | JOHNNY MIRANDA |
| Gas Piping or Gas Test | 2/16/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pool Piping | 2/16/2022 | Approved | JOHNNY MIRANDA |
| Pre-Gunite | 2/16/2022 | Approved | JOHNNY MIRANDA |
| Rough-Electrical | 2/16/2022 | Approved | JOHNNY MIRANDA |
| Rough-Plumbing | 2/16/2022 | Approved | JOHNNY MIRANDA |
| Deputy Shotcrete | 2/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deck | 3/10/2022 | Approved | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 6/21/2022 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 12/5/2023 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 12/19/2023 | Approved | ANDEY CHAPARRO |
| Final | 5/6/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 5/7/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |