10932 W SAVONA ROAD 90077

Certificate Information: 10932 W SAVONA ROAD 90077

Application / Permit
20047-20000-01064
Plan Check / Job No.
B20VN09139
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32'-6" X 13'-3" POOL WITH 10' X 10' SPA ON PILES ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/4/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/6/2020 OMID HEDAYAT
Building Plans Picked Up 8/7/2020 APPLICANT
Plan Check Approved 9/10/2020 SEWADA ZADOORAN MILAGARDI
Issued 9/10/2020 APPLICANT
CofO in Progress 10/28/2021 CHRISTOPHER WILSON
Permit Finaled 11/24/2021 DANIEL ORRANTE
CofO Issued 11/24/2021 DANIEL ORRANTE
Permit Finaled 11/24/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/10/2020 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Abrahamian,, Zaven; Lic. No.: C41672 237 S LAMER ST      BURBANK, CA 91506
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2020 Partial Approval CHRISTOPHER WILSON
Final 10/8/2020 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 10/8/2020 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 11/18/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/18/2020 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 11/19/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/9/2021 Approved CHRISTOPHER WILSON
Grounding or Bonding 2/9/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 2/9/2021 Partial Approval CHRISTOPHER WILSON
Pre-Gunite 2/9/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 2/9/2021 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 5/28/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 6/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 6/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 6/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 6/15/2021 Approved CHRISTOPHER WILSON
Enclosure/Fence 6/15/2021 Not Ready for Inspection CHRISTOPHER WILSON
Posting Pre-Inspection 7/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Final 7/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pool Equipment Noise Test 7/7/2021 Approved ROBERT CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/7/2021 SGSOV Approved CHRISTOPHER WILSON
Final 9/3/2021 Corrections Issued CHRISTOPHER WILSON
Final 10/28/2021 Conditional Approval CHRISTOPHER WILSON