1060 N FORTUNE WAY 90042

Certificate Information: 1060 N FORTUNE WAY 90042

Application / Permit
20047-20000-01010
Plan Check / Job No.
B20VN08811
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 35' X 13' IRR.-SHAPED POOL W/ 6' X 6' SPA PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
CofO Issued on 3/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 JENNIFER LEE
Corrections Issued 7/9/2020 JENNIFER LEE
Plan Check Approved 8/4/2020 GURUNATH NESARAJAH
Issued 8/20/2020 APPLICANT
CofO in Progress 3/1/2021 COREY HUPP
CofO in Progress 3/2/2021 COREY HUPP
Permit Finaled 3/6/2021 DEROLD HAUFF
CofO Issued 3/6/2021 DEROLD HAUFF
Permit Finaled 3/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/9/2020 JENNIFER LEE
Construction near power lines Cleared 7/18/2020 WALTER RAMIREZ
Construction within easement Cleared 7/18/2020 WALTER RAMIREZ
Work Adjacent to Public Way Cleared 7/22/2020 ARMEN SARKISIAN
Eng Process Fee Ord 176,300 Cleared 7/30/2020 ROSA SILVA

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 8/25/2020 Not Ready for Inspection ENRIQUE MIRELES
Pool Piping 8/25/2020 Not Ready for Inspection ENRIQUE MIRELES
Pre-Gunite 8/25/2020 Corrections Issued ENRIQUE MIRELES
Rough-Electrical 8/25/2020 Not Ready for Inspection ENRIQUE MIRELES
Pool Piping 8/28/2020 Approved HAMIK HARTOUNIAN
Pre-Gunite 8/28/2020 Conditional Approval HAMIK HARTOUNIAN
Special/Order Compliance 8/28/2020 Approved CHRISTOPHER DELLEFIELD
Enclosure/Fence 10/29/2020 Not Ready for Inspection COREY HUPP
Deck 10/30/2020 Approved COREY HUPP
Enclosure/Fence 10/30/2020 Approved COREY HUPP
Excavation/Setback/Form/Re-Bar 11/25/2020 Approved COREY HUPP
Final 11/25/2020 Not Ready for Inspection COREY HUPP
Pre-Gunite 11/25/2020 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Not Ready COREY HUPP
Equipment Noise Level 12/7/2020 Approved DA LIU
Final 12/8/2020 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Not Ready COREY HUPP
Final 12/17/2020 OK to Issue CofO COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Not Required COREY HUPP