10826 W WESTMINSTER AVE 90034
Certificate Information: 10826 W WESTMINSTER AVE 90034
- Application / Permit
- 20047-20000-01003
- Plan Check / Job No.
- B20VN08778
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW SWIMMING POOL W/ SPA PER CITY STD PLAN #268 & SUPPL DETAIL OF POOL COVER VAULT.
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 7/8/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/10/2021 | HAYATO TSUCHIYA |
| Issued | 5/10/2021 | APPLICANT |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| CofO in Progress | 2/9/2022 | JOHNNY MIRANDA |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
| CofO Issued | 2/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/11/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/13/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Pre-Gunite | 7/21/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Enclosure/Fence | 11/4/2021 | Corrections Issued | JOHNNY MIRANDA |
| Enclosure/Fence | 11/15/2021 | Corrections Issued | RYAN SALAZAR |
| Pool Equipment Noise Test | 12/3/2021 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/25/2022 | Corrections Issued | JOHNNY MIRANDA |
| Pre-Gunite | 1/25/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 2/9/2022 | Approved | JOHNNY MIRANDA |
| Final | 2/9/2022 | OK to Issue CofO | JOHNNY MIRANDA |