15566 W CHASMILA DR 91436

Certificate Information: 15566 W CHASMILA DR 91436

Application / Permit
20047-20000-01000
Plan Check / Job No.
B20VN08762
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL ( 10 X 20 ), STANDARD PLAN 270
Permit Issued
Issued on 7/5/2022
Issuing Office
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 TSE MING HUANG
Corrections Issued 8/25/2020 TSE MING HUANG
Plan Check Approved 5/13/2022 YAQUB MIRZA
Building Plans Picked Up 5/17/2022 APPLICANT
Issued 7/5/2022 APPLICANT
CofO in Progress 10/10/2024 SEAN WIRCH
CofO Issued 10/22/2024 JOHN JANSON
Permit Finaled 10/22/2024 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gunite 10/12/2023 Corrections Issued VINCENT HANLEY
Pool Piping 10/12/2023 Corrections Issued VINCENT HANLEY
Pre-Gunite 10/12/2023 Corrections Issued VINCENT HANLEY
Rough-Electrical 10/12/2023 Corrections Issued VINCENT HANLEY
Rough-Plumbing 10/12/2023 Corrections Issued VINCENT HANLEY
Pre-Gunite 11/7/2023 Corrections Issued VINCENT HANLEY
Gas Piping or Gas Test 11/16/2023 Approved VINCENT HANLEY
Pool Piping 11/16/2023 Partial Approval VINCENT HANLEY
Deputy Shotcrete 11/20/2023 Partial Approval VINCENT HANLEY
Enclosure/Fence 12/19/2023 Approved VINCENT HANLEY
Grounding or Bonding 12/19/2023 Approved VINCENT HANLEY
Enclosure/Fence 12/20/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 5/6/2024 Approved VINCENT HANLEY
Final 5/6/2024 Partial Approval VINCENT HANLEY
Pool Equipment Noise Test 5/6/2024 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved VINCENT HANLEY
Final 10/9/2024 Corrections Issued ALEXANDER HANDY