4316 N KLUMP AVE 91602

Certificate Information: 4316 N KLUMP AVE 91602

Application / Permit
20047-20000-00955
Plan Check / Job No.
B20VN08473
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 30' POOL PER LA CITY STANDARD PLAN #270
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 1/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/7/2020 JENNIFER LEE
Corrections Issued 8/10/2020 JENNIFER LEE
Plan Check Approved 9/2/2020 JENNIFER LEE
Issued 9/2/2020 APPLICANT
CofO in Progress 1/23/2023 DAVID MATSON
Permit Finaled 1/24/2023 MICHAEL SMITH
CofO Issued 1/24/2023 MICHAEL SMITH
Permit Finaled 1/24/2023 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Steele Builders Inc; Lic. No.: 1037702-B 23100 COLLINS STREET      WOODLAND HILLS, CA 91367
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/4/2020 Not Ready for Inspection THOMAS FINNILA
Pre-Gunite 9/10/2020 Approved BRENDAN LOONEY
Enclosure/Fence 4/6/2021 Corrections Issued JOHN HAYES
Enclosure/Fence 4/13/2021 Not Ready for Inspection THOMAS FINNILA
Grounding or Bonding 4/13/2021 Not Ready for Inspection THOMAS FINNILA
Enclosure/Fence 4/21/2021 Corrections Issued THOMAS FINNILA
Grounding or Bonding 4/21/2021 Not Ready for Inspection THOMAS FINNILA
Pool Equipment Noise Test 5/14/2021 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 5/25/2021 Approved ARAM AVEDISIAN
Final 5/25/2021 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Not Ready ARAM AVEDISIAN
Final 6/3/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved THOMAS FINNILA
Final 7/19/2021 Not Ready for Inspection THOMAS FINNILA
Final 3/4/2022 Not Ready for Inspection THOMAS FINNILA
Final 3/9/2022 Not Ready for Inspection THOMAS FINNILA
Final 3/16/2022 Partial Approval THOMAS FINNILA
Final 1/23/2023 OK to Issue CofO DAVID MATSON