4316 N KLUMP AVE 91602
Certificate Information: 4316 N KLUMP AVE 91602
- Application / Permit
- 20047-20000-00955
- Plan Check / Job No.
- B20VN08473
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 30' POOL PER LA CITY STANDARD PLAN #270
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | JENNIFER LEE |
| Corrections Issued | 8/10/2020 | JENNIFER LEE |
| Plan Check Approved | 9/2/2020 | JENNIFER LEE |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 1/23/2023 | DAVID MATSON |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Steele Builders Inc; Lic. No.: 1037702-B | 23100 COLLINS STREET WOODLAND HILLS, CA 91367 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/10/2020 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 4/6/2021 | Corrections Issued | JOHN HAYES |
| Enclosure/Fence | 4/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Grounding or Bonding | 4/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Enclosure/Fence | 4/21/2021 | Corrections Issued | THOMAS FINNILA |
| Grounding or Bonding | 4/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pool Equipment Noise Test | 5/14/2021 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | ARAM AVEDISIAN |
| Final | 5/25/2021 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 6/3/2021 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/3/2021 | SGSOV Approved | THOMAS FINNILA |
| Final | 7/19/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 3/4/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 3/9/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 3/16/2022 | Partial Approval | THOMAS FINNILA |
| Final | 1/23/2023 | OK to Issue CofO | DAVID MATSON |