1051 N HARTZELL ST 90272

Certificate Information: 1051 N HARTZELL ST 90272

Application / Permit
20047-20000-00948
Plan Check / Job No.
B20VN08443
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREGULAR 14'-0" X 30'-0" POOL W/ 5'-0" X 7'-0" SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
CofO Issued on 12/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2020 APPLICANT
Assigned to Plan Check Engineer 7/4/2020 JENNIFER LEE
Corrections Issued 7/4/2020 JENNIFER LEE
Plan Check Approved 11/2/2020 JENNIFER LEE
Issued 11/4/2020 APPLICANT
CofO in Progress 11/29/2021 ANDREW NAVE
Permit Finaled 12/1/2021 DANIEL ORRANTE
CofO Issued 12/1/2021 DANIEL ORRANTE
Permit Finaled 12/1/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/5/2020 JENNIFER LEE
Construction near power lines Cleared 10/19/2020 RIDWAN HARDY
Construction within easement Cleared 10/19/2020 RIDWAN HARDY

Contact Information

Contractor Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 3/19/2021 Partial Approval JOHN KIDWELL
Pool Piping 3/19/2021 Approved JOHN KIDWELL
Pre-Gunite 3/19/2021 Approved JOHN KIDWELL
Deck 8/25/2021 Approved JUAN VALENZUELA
Enclosure/Fence 8/31/2021 Corrections Issued JUAN VALENZUELA
Enclosure/Fence 9/10/2021 Approved KENNETH NAGLE
Pool Equipment Noise Test 10/4/2021 Approved JAMES VORHIS
Excavation/Setback/Form/Re-Bar 10/19/2021 Approved JOHN KIDWELL
Final 10/19/2021 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved JOHN KIDWELL
Final 11/15/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 11/29/2021 Approved ANDREW NAVE
Final 11/29/2021 OK to Issue CofO ANDREW NAVE