2201 N MALAGA ROAD 90068
Certificate Information: 2201 N MALAGA ROAD 90068
- Application / Permit
- 20047-20000-00943
- Plan Check / Job No.
- B20VN08415
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) IRREGULAR SHAPED 24' X 12' POOL WITH (N) IRREGULAR SHAPED10'6" X 12' SPA ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/19/2020 | APPLICANT |
| Plan Check Approved | 10/29/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/29/2020 | APPLICANT |
| CofO in Progress | 8/10/2021 | BRIAN SULLIVAN |
| No Progress | 4/5/2022 | RUBEN SALAS |
| CofO in Progress | 4/6/2022 | BRIAN SULLIVAN |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
| CofO Issued | 3/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/18/2020 | TRACY WILLIAMS |
| Roof/Waste drainage to street | Cleared | 10/19/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 10/29/2020 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/30/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Other (see comments) | 1/12/2021 | Conditional Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 2/2/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Other (see comments) | 2/11/2021 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Other (see comments) | 3/9/2021 | Conditional Approval | BRIAN SULLIVAN |
| Pre-Gunite | 4/13/2021 | Approved | BRIAN SULLIVAN |
| Deputy Shotcrete | 4/15/2021 | No Access for Inspection | BRAD BESCOS |
| ELECTRICAL-Final | 6/30/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Piping or Gas Test | 6/30/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/30/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pool Equipment Noise Test | 6/30/2021 | Not Ready for Inspection | ROBERT CHAVEZ |
| Enclosure/Fence | 7/12/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 7/12/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 7/19/2021 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 7/19/2021 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 7/21/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/4/2021 | Approved | RAUL BARAJAS |
| Final | 8/4/2021 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 8/4/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | RAUL BARAJAS |
| Final | 8/9/2021 | OK to Issue CofO | BRIAN SULLIVAN |