9701 W OAKMORE ROAD 90035

Certificate Information: 9701 W OAKMORE ROAD 90035

Application / Permit
20047-20000-00929
Plan Check / Job No.
B20VN08328
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 28' POOL W/ 6' X 6' SPA PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 8/12/2020
Issuing Office
Current Status
CofO Issued on 11/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 JENNIFER LEE
Corrections Issued 6/27/2020 JENNIFER LEE
Plan Check Approved 7/27/2020 RAPHAEL ROSAS
Issued 8/12/2020 APPLICANT
CofO in Progress 11/5/2020 KEVIN SARGSYAN
CofO Issued 11/17/2020 VINCENT COTTON
Permit Finaled 11/17/2020 VINCENT COTTON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/29/2020 JENNIFER LEE
Construction near power lines Cleared 7/8/2020 WALTER RAMIREZ
Construction within easement Cleared 7/8/2020 WALTER RAMIREZ

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2020 Approved KEVIN SARGSYAN
Pool Piping 8/18/2020 Approved KEVIN SARGSYAN
Pre-Gunite 8/18/2020 Conditional Approval KEVIN SARGSYAN
Grounding or Bonding 9/4/2020 Approved KEVIN SARGSYAN
Enclosure/Fence 9/11/2020 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 9/14/2020 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 9/15/2020 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Not Ready KEVIN SARGSYAN
Final 10/22/2020 Corrections Issued KEVIN SARGSYAN
Pool Equipment Noise Test 10/27/2020 Approved ROBERT CHAVEZ
Final 10/28/2020 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 10/28/2020 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Not Ready KEVIN SARGSYAN
ELECTRICAL-Final 11/4/2020 Approved KEVIN SARGSYAN
Final 11/4/2020 Conditional Approval KEVIN SARGSYAN
Pre-Gunite 11/4/2020 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Approved KEVIN SARGSYAN