9701 W OAKMORE ROAD 90035
Certificate Information: 9701 W OAKMORE ROAD 90035
- Application / Permit
- 20047-20000-00929
- Plan Check / Job No.
- B20VN08328
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 28' POOL W/ 6' X 6' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 8/12/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | JENNIFER LEE |
| Corrections Issued | 6/27/2020 | JENNIFER LEE |
| Plan Check Approved | 7/27/2020 | RAPHAEL ROSAS |
| Issued | 8/12/2020 | APPLICANT |
| CofO in Progress | 11/5/2020 | KEVIN SARGSYAN |
| CofO Issued | 11/17/2020 | VINCENT COTTON |
| Permit Finaled | 11/17/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/29/2020 | JENNIFER LEE |
| Construction near power lines | Cleared | 7/8/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 7/8/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Approved | KEVIN SARGSYAN |
| Pool Piping | 8/18/2020 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 8/18/2020 | Conditional Approval | KEVIN SARGSYAN |
| Grounding or Bonding | 9/4/2020 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 9/11/2020 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 9/14/2020 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 9/15/2020 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 10/22/2020 | Corrections Issued | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 10/27/2020 | Approved | ROBERT CHAVEZ |
| Final | 10/28/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Gunite | 10/28/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Not Ready | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/4/2020 | Approved | KEVIN SARGSYAN |
| Final | 11/4/2020 | Conditional Approval | KEVIN SARGSYAN |
| Pre-Gunite | 11/4/2020 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Approved | KEVIN SARGSYAN |