6430 W DREXEL AVE 90048
Certificate Information: 6430 W DREXEL AVE 90048
- Application / Permit
- 20047-20000-00866
- Plan Check / Job No.
- B20VN07959
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'-0" X 16'-0" SWIMMING POOL PER STANDARD PLAN #268
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/24/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/14/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/15/2020 | JEROME MAGAT PALMA |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 9/6/2022 | MICHAEL PELHAM |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction within easement | Cleared | 8/21/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Approved | EVAN COOPER |
| Gas Piping or Gas Test | 8/13/2021 | Approved | EVAN COOPER |
| Rough-Electrical | 8/13/2021 | Approved | EVAN COOPER |
| Rough-Plumbing | 8/13/2021 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/24/2021 | Corrections Issued | EVAN COOPER |
| Special/Order Compliance | 8/25/2021 | Not Ready for Inspection | EVAN COOPER |
| Grounding or Bonding | 3/1/2022 | Partial Approval | EVAN COOPER |
| Enclosure/Fence | 6/24/2022 | Approved | EVAN COOPER |
| Pool Equipment Noise Test | 8/8/2022 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 8/18/2022 | Approved | EVAN COOPER |
| Final | 8/18/2022 | Corrections Issued | EVAN COOPER |
| Pre-Gunite | 8/18/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | EVAN COOPER |
| Final | 9/6/2022 | OK to Issue CofO | MICHAEL PELHAM |