4217 N NAVAJO ST 91602
Certificate Information: 4217 N NAVAJO ST 91602
- Application / Permit
- 20047-20000-00752
- Plan Check / Job No.
- B20VN05394
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' x 9' SEMI-CIRCULAR SHAPED SPA PER L.A. STANDARD PLAN #265
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Current Status
- CofO Issued on 6/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 5/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 6/1/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 6/10/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 6/23/2020 | SERGIO MUNIZ |
| Plan Check Approved | 7/8/2020 | ROSENDO MEDINA |
| Issued | 7/14/2020 | APPLICANT |
| CofO in Progress | 4/5/2021 | ARAM AVEDISIAN |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
| CofO Issued | 6/19/2021 | MICHAEL SMITH |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 6/8/2020 | LAUREN PADICK |
Contact Information
| Contractor | T & D Construction Unlimited Inc; Lic. No.: 1003171-B | 4107 EAST AVENUE S10 PALMDALE, CA 93552 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/16/2020 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/20/2020 | Approved | THOMAS FINNILA |
| Deputy Shotcrete | 7/21/2020 | Conditional Approval | THOMAS FINNILA |
| Deck | 12/17/2020 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Pool Equipment Noise Test | 3/11/2021 | Approved | FELIPE PENICHE |
| Final | 3/17/2021 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Approved | THOMAS FINNILA |
| Grading Pre-Inspection | 3/23/2021 | Partial Inspection | THOMAS FINNILA |
| Final | 4/5/2021 | OK to Issue CofO | ARAM AVEDISIAN |