5225 N FULTON AVE 91401
Certificate Information: 5225 N FULTON AVE 91401
- Application / Permit
- 20047-20000-00741
- Plan Check / Job No.
- B20VN07293
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 40' x 15' POOL AND SPA PER STD. PLAN # 268 AND ENG. DETAIL #649
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofO Issued on 11/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | JEFFREY TANGONAN |
| Corrections Issued | 7/10/2020 | JEFFREY TANGONAN |
| Plan Check Approved | 8/4/2020 | SERGIO MUNIZ |
| Issued | 8/31/2020 | APPLICANT |
| CofO in Progress | 11/5/2021 | MICHAEL PELHAM |
| CofO Issued | 11/6/2021 | MICHAEL SMITH |
| Permit Finaled | 11/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Dynamic Construction Pools & Spas; Lic. No.: 652598-C53 | 12522 BRADLEY AVENUE SYLMAR, CA 91342 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/15/2020 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 9/17/2020 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 9/22/2020 | Partial Approval | CHARLES POWELL |
| Deck | 10/13/2020 | Corrections Issued | CHARLES POWELL |
| Enclosure/Fence | 5/11/2021 | Corrections Issued | CHARLES POWELL |
| Enclosure/Fence | 5/20/2021 | Partial Approval | DAVID MATSON |
| Enclosure/Fence | 5/28/2021 | Approved | CHARLES POWELL |
| Deck | 6/7/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 10/13/2021 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | MISAEL ESPARZA |
| Equipment Noise Level | 10/18/2021 | Approved | FELIPE PENICHE |
| Final | 10/22/2021 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/28/2021 | Approved | MICHEL ABAJAN |
| Final | 10/28/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 10/28/2021 | Approved | MICHEL ABAJAN |
| Final | 11/5/2021 | OK to Issue CofO | MICHAEL PELHAM |