240 N ROCKINGHAM AVE 90049
Certificate Information: 240 N ROCKINGHAM AVE 90049
- Application / Permit
- 20047-20000-00733
- Plan Check / Job No.
- B20VN07225
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 21'-6" X 56'-10" POOL & 9' X 10' SPA PER STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | RAPHAEL ROSAS |
| Corrections Issued | 6/19/2020 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Plan Check Approved | 7/20/2020 | RAPHAEL ROSAS |
| Issued | 8/5/2020 | APPLICANT |
| CofO in Progress | 11/4/2022 | JUAN VALENZUELA |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
| CofO Issued | 11/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/20/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Davis Steve & Sons Pools Inc; Lic. No.: 586825-C53 | 1258 LAMONT AVE THOUSAND OAKS, CA 91362 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/1/2020 | Approved | TIM CHRISTENSEN |
| Pool Piping | 9/1/2020 | Partial Approval | TIM CHRISTENSEN |
| Pre-Gunite | 9/1/2020 | Approved | TIM CHRISTENSEN |
| Deputy Shotcrete | 9/8/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 9/8/2020 | Corrections Issued | ROBERT SHELLY |
| Grounding or Bonding | 6/7/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Piping or Gas Test | 6/15/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Grounding or Bonding | 6/15/2022 | Corrections Issued | JUAN VALENZUELA |
| Rough-Electrical | 6/15/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Grounding or Bonding | 6/29/2022 | Approved | JUAN VALENZUELA |
| Rough-Plumbing | 7/15/2022 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 7/28/2022 | Not Ready for Inspection | ANDREW NAVE |
| Enclosure/Fence | 8/1/2022 | Approved | ANDREW NAVE |
| Pool Equipment Noise Test | 9/28/2022 | Approved | JAMES VORHIS |
| Final | 10/4/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 11/4/2022 | Conditional Approval | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | JUAN VALENZUELA |