909 N GREENTREE ROAD 90272
Certificate Information: 909 N GREENTREE ROAD 90272
- Application / Permit
- 20047-20000-00662
- Plan Check / Job No.
- B20VN06760
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 26' POOL WITH 7' X 7' SPA
- Permit Issued
- Issued on 8/10/2020
- Issuing Office
- Current Status
- CofO Issued on 7/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2020 | ROSENDO MEDINA |
| Corrections Issued | 5/19/2020 | ROSENDO MEDINA |
| Plan Check Approved | 8/10/2020 | ANGELICA MARTINEZ |
| Issued | 8/10/2020 | APPLICANT |
| CofO in Progress | 6/30/2021 | JOHN KIDWELL |
| CofO Issued | 7/14/2021 | VINCENT COTTON |
| Permit Finaled | 7/14/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/26/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 6/26/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 6/26/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/24/2020 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 8/10/2020 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 8/10/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 1/11/2021 | Partial Approval | JOHN KIDWELL |
| Pool Piping | 1/11/2021 | Conditional Approval | JOHN KIDWELL |
| Pre-Gunite | 1/11/2021 | Conditional Approval | JOHN KIDWELL |
| Deck | 2/17/2021 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 2/17/2021 | Approved | JOHN KIDWELL |
| Deck | 2/19/2021 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 2/19/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 3/22/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Enclosure/Fence | 3/24/2021 | Approved | JOHN KIDWELL |
| Pool Equipment Noise Test | 4/6/2021 | Approved | JAMES VORHIS |
| Enclosure/Fence | 4/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Approved | JOHN KIDWELL |
| Final | 4/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Pool/Spa Cover | 4/7/2021 | Approved | JOHN KIDWELL |
| Pre-Gunite | 4/7/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Not Ready | JOHN KIDWELL |
| Final | 6/9/2021 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Enclosure/Fence | 6/14/2021 | Approved | JOHN KIDWELL |
| Final | 6/14/2021 | OK to Issue CofO | JOHN KIDWELL |
| Pool/Spa Cover | 6/14/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | JOHN KIDWELL |