615 S ARDEN BLVD 90005

Certificate Information: 615 S ARDEN BLVD 90005

Application / Permit
20047-20000-00635
Plan Check / Job No.
B20VN06457
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 50' X 20' POOL WITH 9' X 8' SPA PER STANDARD PLAN #268. AUTO POOL COVER PER ENGINEER DETAIL.
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/8/2020 ROSENDO MEDINA
Corrections Issued 5/11/2020 ROSENDO MEDINA
Applicant returned to address corrections 6/25/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/27/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/18/2020 ROSENDO MEDINA
Plan Check Approved 9/21/2020 ROSENDO MEDINA
Issued 9/29/2020 APPLICANT
CofO in Progress 10/26/2021 ARTHUR SARGSYAN
CofO in Progress 10/26/2021 ARTHUR SARGSYAN
Permit Finaled 10/27/2021 DEROLD HAUFF
CofO Issued 10/27/2021 DEROLD HAUFF
Permit Finaled 10/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 5/12/2020 WALTER RAMIREZ
HPOZ Cleared 5/28/2020 HERMINIGILDO AGUSTIN
Specific Plan Cleared 5/28/2020 HERMINIGILDO AGUSTIN
ZI Cleared 5/28/2020 HERMINIGILDO AGUSTIN
Construction near power lines Cleared 8/12/2020 RIDWAN HARDY

Contact Information

Contractor Medina Rafael; Lic. No.: 1061571-C53 8605 SPOHN DR      FONTANA, CA 92335
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/2/2020 Approved ARTHUR SARGSYAN
Enclosure/Fence 7/6/2021 Approved CHRIS CHRISTENSEN
Gas Piping or Gas Test 9/20/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 9/24/2021 Approved JOSEPH MCGARRY
Final 9/24/2021 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved JOSEPH MCGARRY
Final 10/6/2021 OK to Issue CofO ARTHUR SARGSYAN