4542 N MORELLA AVE 91607

Certificate Information: 4542 N MORELLA AVE 91607

Application / Permit
20047-20000-00626
Plan Check / Job No.
B20VN06416
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12'-0' X 40'-0" SWIMING POOL AND 8'-0" x 12'-0" SPA WITHIN PER STD PLAN # 268.
Permit Issued
Issued on 5/29/2020
Issuing Office
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 TROY DEGUZMAN
Corrections Issued 5/12/2020 TROY DEGUZMAN
Building Plans Picked Up 5/13/2020 APPLICANT
Issued 5/29/2020 APPLICANT
CofO in Progress 4/13/2021 THOMAS FINNILA
CofO in Progress 4/13/2021 THOMAS FINNILA
Permit Finaled 5/8/2021 MICHAEL SMITH
CofO Issued 5/8/2021 MICHAEL SMITH
Permit Finaled 5/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction within easement Cleared 5/29/2020 OSCAR CASTRO

Contact Information

Contractor Agam Pool And Spa Inc; Lic. No.: 993464-C53 12940 ADDISON STREET      SHERMAN OAKS, CA 91423
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 10/30/2020 Approved THOMAS FINNILA
Deck 1/14/2021 Approved THOMAS FINNILA
Grounding or Bonding 1/14/2021 Partial Approval THOMAS FINNILA
Enclosure/Fence 2/5/2021 Corrections Issued THOMAS FINNILA
Enclosure/Fence 2/8/2021 Not Ready for Inspection THOMAS FINNILA
Enclosure/Fence 2/10/2021 Not Ready for Inspection THOMAS FINNILA
Pool Equipment Noise Test 2/17/2021 No Access for Inspection ROBERT GOLD
Pool Equipment Noise Test 2/22/2021 Corrections Issued ROBERT GOLD
Pool Equipment Noise Test 2/26/2021 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 3/5/2021 Approved THOMAS FINNILA
Final 3/5/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Approved THOMAS FINNILA
Final 3/11/2021 Corrections Issued THOMAS FINNILA
Final 3/24/2021 Partial Approval THOMAS FINNILA
Final 4/13/2021 OK to Issue CofO THOMAS FINNILA