871 N LEONARD ROAD 90049

Certificate Information: 871 N LEONARD ROAD 90049

Application / Permit
20047-20000-00618
Plan Check / Job No.
B20VN06346
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'-0" X 32'-6" SWIMMING POOL AND 16'-0" X 6'-0" SPA PER LA CITY STANDARD PLAN #268 AND ENGINEER DETAIL #551 & #672
Permit Issued
Issued on 6/23/2020
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 JEROME MAGAT PALMA
Corrections Issued 5/7/2020 JEROME MAGAT PALMA
Plan Check Approved 6/9/2020 GURUNATH NESARAJAH
Issued 6/23/2020 APPLICANT
CofO in Progress 2/16/2023 KENNETH NAGLE
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 5/22/2020 MARC WOERSCHING
Miscellaneous Cleared 5/22/2020 MARC WOERSCHING
Miscellaneous Cleared 5/22/2020 MARC WOERSCHING
Miscellaneous Cleared 5/29/2020 NOAH MCCOY

Contact Information

Contractor Design Management And Construction Services; Lic. No.: 856999-B 26007 HUNTINGTON LANE STE 7      VALENCIA, CA 91355
Contractor Design Management And Construction Services; Lic. No.: 856999-C53 26007 HUNTINGTON LANE STE 7      VALENCIA, CA 91355
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2020 Not Ready for Inspection TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/9/2020 Conditional Approval TIM CHRISTENSEN
FLOOD-Proofing Certificate 7/9/2020 Approved TIM CHRISTENSEN
Pool Piping 7/9/2020 Partial Inspection TIM CHRISTENSEN
Pre-Gunite 7/9/2020 Approved TIM CHRISTENSEN
Deputy Shotcrete 7/14/2020 Conditional Approval TIM CHRISTENSEN
Gas Piping or Gas Test 7/17/2020 Approved TIM CHRISTENSEN
Pool Piping 7/17/2020 Approved TIM CHRISTENSEN
Deck 11/9/2020 Approved KENNETH NAGLE
Enclosure/Fence 6/16/2022 Approved JUAN VALENZUELA
Pool Equipment Noise Test 9/27/2022 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 9/29/2022 Approved JUAN VALENZUELA
Final 9/29/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved JUAN VALENZUELA
Final 10/28/2022 Conditional Approval JUAN VALENZUELA