11456 W BELLAGIO ROAD 90049

Certificate Information: 11456 W BELLAGIO ROAD 90049

Application / Permit
20047-20000-00605
Plan Check / Job No.
B20VN06265
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSE 15'X42' POOL WITH 7'-6"X8 '-3" ATTACHED SPA WITH POOL COVER SUPPORTED ON PILES AND GRADE BEAMS
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
Issued on 12/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 DAWN MC NULTY
Corrections Issued 5/24/2020 DAWN MC NULTY
Quality Review Completed 5/26/2020 CHON CHIO KUO
Building Plans Picked Up 5/29/2020 APPLICANT
Applicant returned to address corrections 11/17/2020 DAWN MC NULTY
Plan Check Approved 12/9/2020 DAWN MC NULTY
Issued 12/10/2020 APPLICANT

Permit Application Clearance Information

CPC Cleared 6/11/2020 PABLO ESTRADA
Sewer availability Cleared 9/10/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/14/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/26/2020 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 11/18/2020 DAWN MC NULTY
Miscellaneous Cleared 11/18/2020 DAWN MC NULTY

Contact Information

Contractor Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 9018 BALBOA BLVD SUITE 353      NORTHRIDGE, CA 91325
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 12/15/2020 Conditional Approval CARLOS MATAMOROS
Deputy Grading 12/16/2020 Conditional Approval CARLOS MATAMOROS
Deputy Grading 12/17/2020 Conditional Approval CARLOS MATAMOROS
Deputy Grading 12/22/2020 Conditional Approval CARLOS MATAMOROS
Deputy Grading 12/23/2020 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/12/2021 Partial Approval CARLOS MATAMOROS
Deputy Other (see comments) 1/14/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/25/2021 No Access for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 3/2/2021 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/18/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 3/26/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/31/2021 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 4/1/2021 Conditional Approval CARLOS MATAMOROS
Grounding or Bonding 5/17/2021 Approved CARLOS MATAMOROS
Pool Piping 5/17/2021 Approved CARLOS MATAMOROS
Pre-Gunite 5/17/2021 Approved CARLOS MATAMOROS
Deputy Shotcrete 5/24/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/13/2021 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 7/15/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/19/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/21/2021 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 11/10/2021 Corrections Issued CARLOS MATAMOROS
Pre-Inspection 11/10/2021 Corrections Issued CARLOS MATAMOROS
Gas Piping or Gas Test 11/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 12/17/2021 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 1/10/2022 Approved BRENDAN LOONEY
Final 3/25/2022 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Not Ready CARLOS MATAMOROS
Final 4/6/2022 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Not Ready CARLOS MATAMOROS
ELECTRICAL-Final 6/29/2022 Approved CARLOS MATAMOROS
Final 6/29/2022 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Approved CARLOS MATAMOROS