520 S MATEO ST 90013

Certificate Information: 520 S MATEO ST 90013

Application / Permit
20047-20000-00601
Plan Check / Job No.
B20VN06254
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Apartment
Primary Use
(4) Pool/Spa - Public
Work Description
NEW(54' x 18') SWIMMING POOL AT ROOF TOP LEVEL PER LA STD PLAN# 268, DETAIL 660 &100.
Permit Issued
Issued on 12/21/2023
Issuing Office
Valley
Current Status
Permit Finaled on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 TROY DEGUZMAN
Corrections Issued 7/7/2020 TROY DEGUZMAN
Quality Review Completed 7/7/2020 CHON CHIO KUO
Building Plans Picked Up 7/7/2020 APPLICANT
Disabled Access Plans Picked Up 7/7/2020 APPLICANT
Plan Check Approved 12/21/2023 SELLA BENYAMIN
Issued 12/21/2023 APPLICANT
Permit Finaled 9/26/2025 LARRY ARNICK

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/8/2023 MICHAEL SOTO
"Q" conditions Cleared 8/28/2023 JASON CHAN
"T" removal Cleared 8/28/2023 JASON CHAN
CPC Cleared 8/28/2023 JASON CHAN
ZA Case Cleared 8/28/2023 JASON CHAN
DAS Clearance Cleared 12/12/2023 OLLIE CARTER
Public Swimming Pool approval Cleared 12/21/2023 LACDHS APPROVED

Contact Information

Contractor Addison Pools Inc; Lic. No.: 753417-C53 4363 WOODMAN AVENUE      SHERMAN OAKS, CA 91423
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 1/18/2024 Approved LARRY ARNICK
Pre-Gunite 1/18/2024 Approved LARRY ARNICK
Enclosure/Fence 8/23/2024 Not Ready for Inspection RONALD JIMENEZ
METHANE-Barrier 8/23/2024 Approved RONALD JIMENEZ
METHANE-Subgrade 8/23/2024 Approved RONALD JIMENEZ
Enclosure/Fence 8/28/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/25/2024 Not Ready for Inspection LARRY ARNICK
Final 9/25/2024 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Not Ready LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/10/2024 Not Ready for Inspection LARRY ARNICK
Final 10/10/2024 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/31/2024 Not Ready for Inspection LARRY ARNICK
Final 10/31/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/14/2024 Approved LARRY ARNICK
Final 11/14/2024 Not Ready for Inspection LARRY ARNICK