20339 W DELITA DR 91364
Certificate Information: 20339 W DELITA DR 91364
- Application / Permit
- 20047-20000-00592
- Plan Check / Job No.
- B20VN06186
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL SWIMMING POOL; NEW POOL DIMESNIONS ARE 38'-7" X 20'; ADD NEW 9'-8" X 11'-8" SPA; ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 5/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | SELLA BENYAMIN |
| Corrections Issued | 5/27/2020 | SELLA BENYAMIN |
| Quality Review Completed | 5/27/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| Plan Check Approved | 8/4/2020 | SELLA BENYAMIN |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 5/10/2021 | DAVID SANDOVAL |
| CofO Issued | 5/10/2021 | MICHAEL SMITH |
| Permit Finaled | 5/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pacific Outdoor Living; Lic. No.: 715731-B | 8309 TUJUNGA AVE SUITE 201 SUN VALLEY, CA 91352 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/12/2020 | Corrections Issued | HENRY KIM |
| Piling/Pier/Caisson | 9/15/2020 | Approved | RONALD COWAN |
| Piling/Pier/Caisson | 10/9/2020 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Approved | PAUL CHOPP |
| Rough-Plumbing | 10/22/2020 | Approved | PAUL CHOPP |
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Approved | MICHAEL TEMPLE |
| Gas Piping or Gas Test | 11/12/2020 | Approved | MICHAEL TEMPLE |
| Grounding or Bonding | 11/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Rough-Electrical | 11/12/2020 | Approved | MICHAEL TEMPLE |
| Grounding or Bonding | 11/25/2020 | Partial Approval | STEVEN BACK |
| Enclosure/Fence | 2/9/2021 | Corrections Issued | PAUL CHOPP |
| Enclosure/Fence | 2/10/2021 | Approved | PAUL CHOPP |
| Equipment Noise Level | 4/5/2021 | Approved | FELIPE PENICHE |
| Final | 4/5/2021 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | RONALD COWAN |
| Final | 5/6/2021 | Partial Approval | DAVID SANDOVAL |
| Final | 5/10/2021 | OK to Issue CofO | DAVID SANDOVAL |