9472 W CHEROKEE LANE 90210
Certificate Information: 9472 W CHEROKEE LANE 90210
- Application / Permit
- 20047-20000-00569
- Plan Check / Job No.
- B20VN05982
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMOVE (E) POOL SHELL AND CONSTRUCT NEW 7'-8" x 29'-11" POOL AND SPA ON PILES, ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/21/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 6/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/13/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/23/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/19/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 2/19/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/22/2021 | SEAN SHAHMIRI |
| Issued | 2/26/2021 | APPLICANT |
| CofO in Progress | 8/3/2023 | RAUL BARAJAS |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/19/2021 | SEAN SHAHMIRI |
Contact Information
| Contractor | Haynie Tim; Lic. No.: 980472-B | 531 MAIN STREET #406 EL SEGUNDO, CA 90245 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Partial Inspection | RAUL BARAJAS |
| Grading Pre-Inspection | 5/17/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/17/2022 | Partial Approval | RAUL BARAJAS |
| Posting Pre-Inspection | 5/17/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 5/17/2022 | Corrections Issued | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/20/2022 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Piping or Gas Test | 7/29/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Electrical | 7/29/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Piping or Gas Test | 9/30/2022 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 9/30/2022 | Approved | RAUL BARAJAS |
| Pool Piping | 9/30/2022 | Approved | RAUL BARAJAS |
| Pre-Gunite | 9/30/2022 | Approved | RAUL BARAJAS |
| Deck | 11/16/2022 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 11/29/2022 | Conditional Approval | RAUL BARAJAS |
| Deck | 12/2/2022 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 12/8/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 6/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 6/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 8/3/2023 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Approved | RAUL BARAJAS |