5632 N NORWICH AVE 91411

Certificate Information: 5632 N NORWICH AVE 91411

Application / Permit
20047-20000-00553
Plan Check / Job No.
B20VN05862
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL (26' X 12'-6") & SPA (6' X 6') PER LA CITY STD PLAN #270
Permit Issued
Issued on 11/13/2020
Issuing Office
Current Status
CofO Issued on 6/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 NILOOFAR MEHRAIN
Corrections Issued 6/11/2020 NILOOFAR MEHRAIN
Quality Review Completed 6/11/2020 STEVEN KIM
Building Plans Picked Up 6/11/2020 APPLICANT
Green Plans Picked Up 6/11/2020 APPLICANT
Plan Check Approved 10/27/2020 NILOOFAR MEHRAIN
Issued 11/13/2020 APPLICANT
CofO in Progress 6/23/2022 RICHARD DOCKUS
Permit Finaled 6/23/2022 MICHAEL SMITH
CofO Issued 6/23/2022 MICHAEL SMITH
Permit Finaled 6/23/2022 MICHAEL SMITH

Permit Application Clearance Information

CPC Cleared 8/11/2020 PABLO ESTRADA
Construction near power lines Cleared 10/23/2020 RIDWAN HARDY
Construction within easement Cleared 10/23/2020 RIDWAN HARDY

Contact Information

Contractor Knudsen Mark Curtis; Lic. No.: 544786-B 22639 MIRANDA ST      WOODLAND HILLS, CA 91367
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 11/19/2021 Partial Approval RICHARD DOCKUS
Pre-Gunite 2/25/2022 Corrections Issued RICHARD DOCKUS
Pre-Gunite 3/3/2022 Approved RICHARD DOCKUS
Deputy Shotcrete 3/8/2022 Conditional Approval RYAN SALAZAR
Enclosure/Fence 4/13/2022 Corrections Issued RICHARD DOCKUS
Grounding or Bonding 4/13/2022 Not Ready for Inspection RICHARD DOCKUS
Enclosure/Fence 4/18/2022 Approved RICHARD DOCKUS
Grounding or Bonding 4/18/2022 Corrections Issued RICHARD DOCKUS
Grounding or Bonding 4/20/2022 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/10/2022 Approved RICHARD DOCKUS
Final 5/10/2022 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Approved RICHARD DOCKUS
Equipment Noise Level 5/13/2022 Approved FELIPE PENICHE
Final 6/22/2022 OK to Issue CofO RICHARD DOCKUS