1355 S MEADOWBROOK AVE 90019
Certificate Information: 1355 S MEADOWBROOK AVE 90019
- Application / Permit
- 20047-20000-00549
- Plan Check / Job No.
- B20VN05806
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 33'0"X15'6" SWIMMING POOL WITH 7'0"X9'0" SPA PER ENGINEER
- Permit Issued
- Issued on 4/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Green Plans Picked Up | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | MARVEL DELACRUZ |
| Corrections Issued | 5/11/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 5/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/15/2020 | APPLICANT |
| Applicant returned to address corrections | 8/13/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/25/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 3/3/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 4/1/2021 | MARVEL DELACRUZ |
| Issued | 4/1/2021 | APPLICANT |
| CofO in Progress | 4/1/2022 | JOSE AVILA |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/31/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/31/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Gunite | 4/13/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 4/13/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/28/2021 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 5/28/2021 | Approved | STUART CHAPMAN |
| Gunite | 7/14/2021 | Conditional Approval | RUBEN SALAS |
| Pool Piping | 7/14/2021 | Approved | RUBEN SALAS |
| Pre-Gunite | 7/14/2021 | Approved | RUBEN SALAS |
| Rough-Electrical | 7/14/2021 | Approved | RUBEN SALAS |
| Rough-Plumbing | 7/14/2021 | Approved | RUBEN SALAS |
| Deputy Shotcrete | 7/21/2021 | No Access for Inspection | ELMER BLAND |
| Grounding or Bonding | 9/15/2021 | Approved | STUART CHAPMAN |
| Enclosure/Fence | 11/18/2021 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/5/2022 | Approved | JOSE AVILA |
| Final | 1/5/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Not Ready | JOSE AVILA |
| Enclosure/Fence | 2/3/2022 | Approved | JOSE AVILA |
| Final | 2/3/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Approved | JOSE AVILA |
| Final | 4/1/2022 | OK to Issue CofO | JOSE AVILA |