3535 S PURDUE AVE 90066
Certificate Information: 3535 S PURDUE AVE 90066
- Application / Permit
- 20047-20000-00529
- Plan Check / Job No.
- B20VN05647
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 33' X 15' SWIMMING POOL WITH 9' X 7' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2020 | ROSENDO MEDINA |
| Corrections Issued | 4/23/2020 | ROSENDO MEDINA |
| Plan Check Approved | 5/6/2020 | ROSENDO MEDINA |
| Issued | 6/3/2020 | APPLICANT |
| Permit Finaled | 7/9/2024 | DANIEL ORRANTE |
| CofO Issued | 7/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/24/2020 | ROSENDO MEDINA |
Contact Information
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Plumbing | 6/8/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Corrections Issued | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Corrections Issued | KENNETH NAGLE |
| Pre-Gunite | 6/12/2020 | Approved | KENNETH NAGLE |
| Deputy Shotcrete | 6/23/2020 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Final | 6/26/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/26/2020 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 7/22/2020 | Approved | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 8/13/2020 | Conditional Approval | EVAN COOPER |
| Final | 8/13/2020 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/13/2020 | SGSOV Not Ready | EVAN COOPER |
| Equipment Noise Level | 8/17/2020 | Approved | STEVEN BELTRAN |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 9/4/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/5/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Final | 10/5/2020 | Corrections Issued | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/20/2020 | No Access for Inspection | KENNETH NAGLE |
| Final | 10/20/2020 | No Access for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 10/20/2020 | SGSOV Not Ready | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 11/6/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Approved | EVAN COOPER |
| Final | 11/9/2020 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | EVAN COOPER |