10440 W WHIPPLE ST 91602

Certificate Information: 10440 W WHIPPLE ST 91602

Application / Permit
20047-20000-00525
Plan Check / Job No.
B20VN05567
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW 16' X 40' SWIMMING POOL W/ SPA PER CITY STD PLAN #265.
Permit Issued
Issued on 5/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 HAYATO TSUCHIYA
Corrections Issued 4/21/2020 HAYATO TSUCHIYA
Plan Check Approved 5/15/2020 RAPHAEL ROSAS
Issued 5/26/2020 LADBS
CofO in Progress 10/27/2021 MICHAEL PELHAM
CofO Issued 10/27/2021 MICHAEL SMITH
Permit Finaled 10/27/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2020 Corrections Issued THOMAS FINNILA
Pre-Gunite 10/7/2020 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/9/2020 Approved DAVID MATSON
Gas Piping or Gas Test 10/9/2020 Approved DAVID MATSON
Grounding or Bonding 10/9/2020 Approved DAVID MATSON
Pool Piping 10/9/2020 Approved DAVID MATSON
Pre-Gunite 10/9/2020 Approved DAVID MATSON
Rough-Electrical 10/9/2020 Approved DAVID MATSON
Gas Piping or Gas Test 10/28/2020 Partial Approval THOMAS FINNILA
Grounding or Bonding 7/12/2021 Corrections Issued THOMAS FINNILA
Grounding or Bonding 7/14/2021 Partial Approval THOMAS FINNILA
Enclosure/Fence 8/11/2021 Conditional Approval THOMAS FINNILA
Enclosure/Fence 8/23/2021 Not Ready for Inspection THOMAS FINNILA
Enclosure/Fence 8/24/2021 Not Ready for Inspection THOMAS FINNILA
Enclosure/Fence 8/30/2021 Conditional Approval THOMAS FINNILA
Equipment Noise Level 9/7/2021 Approved FELIPE PENICHE
Final 10/13/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved THOMAS FINNILA
Final 10/27/2021 OK to Issue CofO MICHAEL PELHAM