12255 W RICHWOOD DR 90049
Certificate Information: 12255 W RICHWOOD DR 90049
- Application / Permit
- 20047-20000-00479
- Plan Check / Job No.
- B20VN05262
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 46' X 16' POOL WITH 9'X 9 ' SPA ALL WORK PER STD PLAN #268
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/27/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Plan Check Approved | 7/8/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 7/9/2020 | APPLICANT |
| CofO in Progress | 4/5/2024 | CARLOS MATAMOROS |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
| CofO Issued | 4/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/30/2020 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 6/30/2020 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 6/30/2020 | HERMINIGILDO AGUSTIN |
| Grading Pre-Inspection | Cleared | 7/8/2020 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | California Pools Inc; Lic. No.: 185102-C53 | 901 CALLE AMANECER #115 SAN CLEMENTE, CA 92673 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/21/2020 | No Access for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 9/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 9/3/2020 | Approved | CARLOS MATAMOROS |
| Pool Piping | 9/3/2020 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 9/3/2020 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/10/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deck | 5/11/2022 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 5/19/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 12/16/2022 | No Access for Inspection | JUAN VALENZUELA |
| Enclosure/Fence | 6/5/2023 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 6/22/2023 | Corrections Issued | MICHAEL PELHAM |
| Enclosure/Fence | 7/5/2023 | Approved | CARLOS MATAMOROS |
| Final | 8/21/2023 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 3/28/2024 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Not Ready | EVAN COOPER |
| Final | 4/5/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | CARLOS MATAMOROS |