7463 W FRANKLIN AVE 90046

Certificate Information: 7463 W FRANKLIN AVE 90046

Application / Permit
20047-20000-00421
Plan Check / Job No.
B20VN04805
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12' X 33' SWIMMING POOL PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #400 & #649. SEE COMMENTS
Permit Issued
Issued on 5/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 GURUNATH NESARAJAH
Corrections Issued 3/27/2020 GURUNATH NESARAJAH
Plan Check Approved 5/5/2020 SARKIS HARABEDIAN
Issued 5/26/2020 LADBS
CofO in Progress 11/11/2020 BRIAN SULLIVAN
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/19/2020 GURUNATH NESARAJAH

Contact Information

Contractor T & D Construction Unlimited Inc; Lic. No.: 1003171-B 4107 EAST AVENUE S10      PALMDALE, CA 93552
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/18/2020 Approved BRIAN SULLIVAN
Gas Piping or Gas Test 6/18/2020 Approved BRIAN SULLIVAN
Grounding or Bonding 6/18/2020 Approved BRIAN SULLIVAN
Pool Piping 6/18/2020 Approved BRIAN SULLIVAN
Rough-Electrical 6/18/2020 Approved BRIAN SULLIVAN
Rough-Plumbing 6/18/2020 Approved BRIAN SULLIVAN
Enclosure/Fence 9/4/2020 Corrections Issued BRIAN SULLIVAN
Enclosure/Fence 9/8/2020 Approved BRIAN SULLIVAN
Final 10/5/2020 Not Ready for Inspection BRIAN SULLIVAN
Pre-Gunite 10/5/2020 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Not Ready BRIAN SULLIVAN
Final 10/14/2020 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Not Ready BRIAN SULLIVAN
Final 10/19/2020 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved BRIAN SULLIVAN
Final 11/10/2020 OK to Issue CofO BRIAN SULLIVAN