4046 W 7TH ST 90005

Certificate Information: 4046 W 7TH ST 90005

Application / Permit
20047-20000-00408
Plan Check / Job No.
B20VN04705
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 24' X 17' POOL WITH ATTACHED 6' X 7' SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #271
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 2/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/17/2020 GURUNATH NESARAJAH
Corrections Issued 3/17/2020 GURUNATH NESARAJAH
Plan Check Approved 6/26/2020 RAPHAEL ROSAS
Issued 7/7/2020 APPLICANT
CofO in Progress 1/29/2021 CHRIS CHRISTENSEN
Permit Finaled 2/2/2021 DEROLD HAUFF
CofO Issued 2/2/2021 DEROLD HAUFF
Permit Finaled 2/2/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 3/17/2020 DANG NGUYEN
Miscellaneous Cleared 3/17/2020 DANG NGUYEN
Miscellaneous Cleared 3/17/2020 DANG NGUYEN
Construction near power lines Cleared 5/1/2020 RIDWAN HARDY
Specific Plan Cleared 5/14/2020 CHI DANG
ZI Cleared 5/14/2020 CHI DANG
ZI Cleared 5/20/2020 PABLO ESTRADA

Contact Information

Contractor Dreambuilders Custom Pool & Spa Design; Lic. No.: 1003784-C53 7103 BRENO PL      ALTA LOMA, CA 91701
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 7/22/2020 Approved ENRIQUE MIRELES
Pre-Gunite 7/22/2020 Approved ENRIQUE MIRELES
Deck 12/4/2020 Partial Approval CHRIS CHRISTENSEN
Deck 12/10/2020 Approved SCOTT FINNILA
Grounding or Bonding 12/10/2020 Approved SCOTT FINNILA
Enclosure/Fence 12/16/2020 Corrections Issued CHRIS CHRISTENSEN
Enclosure/Fence 12/21/2020 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/20/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/28/2021 Approved CHRIS CHRISTENSEN
Final 1/28/2021 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Approved CHRIS CHRISTENSEN