5242 N SYLMAR AVE 91401
Certificate Information: 5242 N SYLMAR AVE 91401
- Application / Permit
- 20047-20000-00405
- Plan Check / Job No.
- B20VN04681
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'-0" x 25'-0" POOL WITH 7'-0 " x 5'-0" SPA PER LA CITY STANDARD PLAN# 268.
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 3/17/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/15/2020 | ROSENDO MEDINA |
| Issued | 6/17/2020 | APPLICANT |
| CofO in Progress | 10/30/2020 | MICHEL ABAJAN |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/3/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/2/2020 | Conditional Approval | MISAEL ESPARZA |
| Enclosure/Fence | 8/12/2020 | Corrections Issued | WILLIAM KUEHN |
| Enclosure/Fence | 9/4/2020 | Corrections Issued | DANIEL DREW |
| Enclosure/Fence | 10/13/2020 | Approved | WILLIAM KUEHN |
| Equipment Noise Level | 10/29/2020 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 10/30/2020 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2020 | Approved | MICHEL ABAJAN |
| Final | 10/30/2020 | OK to Issue CofO | MICHEL ABAJAN |
| PLUMBING-Final | 10/30/2020 | Approved | MICHEL ABAJAN |
| Pre-Gunite | 10/30/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | MICHEL ABAJAN |