3732 W BRUNSWICK AVE 90039

Certificate Information: 3732 W BRUNSWICK AVE 90039

Application / Permit
20047-20000-00347
Plan Check / Job No.
B20VN04133
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 30' X 14' POOL WITH A 8' X 8' SPA PER STD PLAN # 268.
Permit Issued
Issued on 3/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/6/2020 PINANK PATEL
Plan Check Approved 3/6/2020 PINANK PATEL
Issued 3/6/2020 LADBS
CofO in Progress 9/3/2020 HAMIK HARTOUNIAN
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2020 Approved HAMIK HARTOUNIAN
Gas Piping or Gas Test 5/15/2020 Approved HAMIK HARTOUNIAN
Pool Piping 5/15/2020 Approved HAMIK HARTOUNIAN
Pre-Gunite 5/15/2020 Approved HAMIK HARTOUNIAN
Deputy Shotcrete 5/19/2020 Conditional Approval HAMIK HARTOUNIAN
Deck 6/5/2020 Conditional Approval HAMIK HARTOUNIAN
Grounding or Bonding 6/5/2020 Approved HAMIK HARTOUNIAN
Enclosure/Fence 6/17/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Enclosure/Fence 6/26/2020 Corrections Issued COREY HUPP
Enclosure/Fence 7/6/2020 Approved HAMIK HARTOUNIAN
Equipment Noise Level 7/9/2020 Not Ready for Inspection ROBERT CHAVEZ
Final 7/10/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Equipment Noise Level 7/15/2020 Approved ROBERT CHAVEZ
Final 7/31/2020 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/31/2020 SGSOV Approved HAMIK HARTOUNIAN
Final 9/3/2020 OK to Issue CofO HAMIK HARTOUNIAN