710 W 155TH ST 90247
Certificate Information: 710 W 155TH ST 90247
- Application / Permit
- 20047-20000-00329
- Plan Check / Job No.
- B20VN03872
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' X 17' POOL WITH AN 8' X 8' SPA PER STD PLAN #268
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 2/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | PINANK PATEL |
| Corrections Issued | 5/7/2020 | PINANK PATEL |
| Plan Check Approved | 7/21/2020 | SERGIO MUNIZ |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 2/12/2021 | ANSON MAGLASANG |
| Permit Finaled | 2/13/2021 | DEROLD HAUFF |
| CofO Issued | 2/13/2021 | DEROLD HAUFF |
| Permit Finaled | 2/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/28/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/28/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Sunset Pools And Spas Inc; Lic. No.: 473735-C53 | 1400 E KATELLA AVE STE 217 ORANGE, CA 92867 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Pool Piping | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Deck | 10/7/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Grounding or Bonding | 10/7/2020 | Corrections Issued | EUGENE CASSIDY |
| Deck | 10/14/2020 | Approved | EUGENE CASSIDY |
| Enclosure/Fence | 11/17/2020 | Corrections Issued | EUGENE CASSIDY |
| Enclosure/Fence | 12/3/2020 | Approved | JOHN KLARIN |
| Deck | 12/10/2020 | Approved | JOSEPH MCGARRY |
| Final | 12/10/2020 | Corrections Issued | JOSEPH MCGARRY |
| Pool Equipment Noise Test | 12/16/2020 | Approved | JAMES VORHIS |
| Pre-Inspection | 12/16/2020 | Corrections Issued | JOHN KLARIN |
| Final | 1/13/2021 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 1/22/2021 | OK to Issue CofO | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Approved | EUGENE CASSIDY |