20129 W JUBILEE WAY 91326
Certificate Information: 20129 W JUBILEE WAY 91326
- Application / Permit
- 20047-20000-00318
- Plan Check / Job No.
- B20VN03810
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 22' x 17' POOL WITH A 6' x 6' SPA PER STANDARD PLAN #254
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/3/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 3/4/2020 | JENNIFER LEE |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 7/19/2021 | DAVID SCANTLIN |
| Permit Finaled | 7/22/2021 | JOHN JANSON |
| CofO Issued | 7/22/2021 | JOHN JANSON |
| Permit Finaled | 7/22/2021 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 3/3/2020 | NOAH MCCOY |
| Grading Pre-Inspection | Cleared | 3/3/2020 | SEAN SHAHMIRI |
| Miscellaneous | Cleared | 3/3/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/3/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/3/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/3/2020 | NOAH MCCOY |
| ZA Case | Cleared | 3/3/2020 | LAUREN PADICK |
| ZA Case | Cleared | 3/3/2020 | LAUREN PADICK |
| ZA Case | Cleared | 3/3/2020 | NOAH MCCOY |
Contact Information
| Contractor | Miller Steven Louis; Lic. No.: 474691-B | 15021 VENTURA BLVD 702 SHERMAN OAKS, CA 91403 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/5/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Gunite | 3/9/2020 | Corrections Issued | DONALD SUNSERI |
| Gunite | 1/5/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/10/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 3/10/2021 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 3/10/2021 | Approved | DAVID SCANTLIN |
| Final | 3/10/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 3/10/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Gunite | 3/10/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Approved | DAVID SCANTLIN |
| Pool Equipment Noise Test | 3/17/2021 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 3/22/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/22/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 3/22/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 6/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 6/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 6/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 6/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 6/22/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 6/22/2021 | Approved | DAVID SCANTLIN |
| Pool Equipment Noise Test | 6/23/2021 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 7/16/2021 | Approved | DAVID SCANTLIN |
| Final | 7/16/2021 | OK to Issue CofO | DAVID SCANTLIN |