1106 N FISKE ST 90272
Certificate Information: 1106 N FISKE ST 90272
- Application / Permit
- 20047-20000-00299
- Plan Check / Job No.
- B20VN03559
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 26' SWIMMING POOL WITH ATTACHED 6' X 6' SPA. ALL WORK PER LA CITY STANDARD PLAN #270.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/3/2020 | GURUNATH NESARAJAH |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 2/1/2021 | JOHN KIDWELL |
| Permit Finaled | 2/1/2021 | VINCENT COTTON |
| CofO Issued | 2/1/2021 | VINCENT COTTON |
| Permit Finaled | 2/1/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/3/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 3/3/2020 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 3/3/2020 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Royal Moon Pools Inc; Lic. No.: 1041907-C53 | 2518 SAN MADRID WAY ROSAMOND, CA 93560 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/22/2020 | Corrections Issued | DANNY TOLENTINO |
| Final | 5/27/2020 | Corrections Issued | DANNY TOLENTINO |
| Pre-Gunite | 5/27/2020 | Approved | DANNY TOLENTINO |
| Deck | 8/19/2020 | Partial Approval | JOHN KIDWELL |
| Deck | 9/14/2020 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 10/19/2020 | Approved | JOHN KIDWELL |
| Rough-Plumbing | 12/18/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Approved | JOHN KIDWELL |
| Final | 1/15/2021 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Approved | JOHN KIDWELL |
| Enclosure/Fence | 1/22/2021 | Approved | JOHN KIDWELL |
| Final | 1/22/2021 | OK to Issue CofO | JOHN KIDWELL |
| Pool/Spa Cover | 1/22/2021 | Approved | JOHN KIDWELL |
| Final | 1/27/2021 | Conditional Approval | JOHN KIDWELL |