20300 W BENTLEY WAY 91326
Certificate Information: 20300 W BENTLEY WAY 91326
- Application / Permit
- 20047-20000-00285
- Plan Check / Job No.
- B20VN03374
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW SWIMMING POOL W/ SPA PER CITY STD PLAN #268. SEE COMMENTS.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | MOHAMMAD ESMAILI |
| Issued | 2/27/2020 | LADBS |
| CofO in Progress | 2/24/2021 | DAVID SCANTLIN |
| CofO Issued | 3/3/2021 | JOHN JANSON |
| Permit Finaled | 3/3/2021 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 2/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/27/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 2/27/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 2/27/2020 | SARAH GOLDMAN |
| ZI | Cleared | 2/27/2020 | SARAH GOLDMAN |
Contact Information
| Contractor | Green Scene The; Lic. No.: 340258-C53 | 21220 DEVONSHIRE ST STE 102 CHATSWORTH, CA 91311 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/24/2020 | Approved | DAVID SCANTLIN |
| Rough-Electrical | 3/24/2020 | Approved | DAVID SCANTLIN |
| Rough-Plumbing | 3/24/2020 | Approved | DAVID SCANTLIN |
| Deck | 4/28/2020 | Approved | DAVID SCANTLIN |
| Grounding or Bonding | 4/28/2020 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 12/3/2020 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | Approved | DAVID SCANTLIN |
| Final | 12/17/2020 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2020 | SGSOV Approved | DAVID SCANTLIN |
| Final | 2/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Equipment Noise Level | 2/23/2021 | Approved | ROBERT GOLD |
| Final | 2/23/2021 | OK to Issue CofO | DAVID SCANTLIN |