946 N EMBURY ST 90272
Certificate Information: 946 N EMBURY ST 90272
- Application / Permit
- 20047-20000-00282
- Plan Check / Job No.
- B20VN03358
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 8' X 8' SPA PER L.A. CITY STANDARD PLAN #265
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- Issued on 7/30/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | ANGELICA DAVE |
| Corrections Issued | 2/26/2020 | ANGELICA DAVE |
| Applicant returned to address corrections | 6/15/2020 | ROSENDO MEDINA |
| Plan Check Approved | 6/15/2020 | ROSENDO MEDINA |
| No Progress | 6/15/2020 | ROSENDO MEDINA |
| Plan Check Approved | 6/29/2020 | JEROME MAGAT PALMA |
| Issued | 7/30/2020 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/11/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/11/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/4/2020 | Corrections Issued | ROBERT SHELLY |
| Gas Piping or Gas Test | 8/4/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Pre-Gunite | 8/4/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Rough-Electrical | 8/4/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Rough-Plumbing | 8/4/2020 | Corrections Issued | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 8/24/2020 | Approved | JOHN KIDWELL |
| Pool Piping | 8/24/2020 | Approved | JOHN KIDWELL |
| Pre-Gunite | 8/24/2020 | Approved | JOHN KIDWELL |
| Rough-Electrical | 8/24/2020 | Approved | JOHN KIDWELL |
| Rough-Plumbing | 8/24/2020 | Approved | JOHN KIDWELL |
| Gas Piping or Gas Test | 9/25/2020 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 12/17/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Grounding or Bonding | 12/28/2020 | No Access for Inspection | KENNETH NAGLE |
| Grounding or Bonding | 12/30/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 12/30/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 1/4/2021 | Partial Approval | ANDREW NAVE |
| Enclosure/Fence | 1/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Grounding or Bonding | 1/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Gunite | 1/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Deck | 1/13/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 1/14/2021 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 1/14/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 1/15/2021 | Approved | JOHN KIDWELL |
| Pool Equipment Noise Test | 1/25/2021 | Approved | JAMES VORHIS |