11661 W LAURELWOOD DR 91604

Certificate Information: 11661 W LAURELWOOD DR 91604

Application / Permit
20047-20000-00272
Plan Check / Job No.
B20VN03270
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW SWIMMING POOL PER CITY STD PLAN # 268. SEE COMMENTS.
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 2/25/2020 HAYATO TSUCHIYA
Plan Check Approved 2/25/2020 HAYATO TSUCHIYA
Issued 2/25/2020 LADBS
CofO in Progress 9/10/2020 ARAM AVEDISIAN
CofO Issued 5/5/2022 DANIEL ORRANTE
Permit Finaled 5/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mr Solar Construction; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/5/2020 Corrections Issued THOMAS FINNILA
Gas Piping or Gas Test 5/14/2020 Not Ready for Inspection THOMAS FINNILA
Pool Piping 5/14/2020 Not Ready for Inspection THOMAS FINNILA
Pre-Gunite 5/14/2020 Not Ready for Inspection THOMAS FINNILA
Rough-Electrical 5/14/2020 Not Ready for Inspection THOMAS FINNILA
Rough-Plumbing 5/14/2020 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/21/2020 Approved ARAM AVEDISIAN
Gas Piping or Gas Test 5/21/2020 Partial Approval ARAM AVEDISIAN
Grounding or Bonding 5/21/2020 Partial Approval ARAM AVEDISIAN
Pool Piping 5/21/2020 Approved ARAM AVEDISIAN
Pre-Gunite 5/21/2020 Partial Approval ARAM AVEDISIAN
Rough-Electrical 5/21/2020 Partial Approval ARAM AVEDISIAN
Grounding or Bonding 6/16/2020 Approved ARAM AVEDISIAN
Enclosure/Fence 6/24/2020 Corrections Issued ARAM AVEDISIAN
Enclosure/Fence 6/30/2020 Approved ARAM AVEDISIAN
Equipment Noise Level 7/8/2020 Not Ready for Inspection RAUL BARAJAS
Equipment Noise Level 7/9/2020 Approved FELIPE PENICHE
Final 9/10/2020 OK to Issue CofO ARAM AVEDISIAN
Pre-Gunite 9/10/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Approved ARAM AVEDISIAN