3509 N LAURELVALE DR 91604

Certificate Information: 3509 N LAURELVALE DR 91604

Application / Permit
20047-20000-00255
Plan Check / Job No.
B20VN03069
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 11'0X 13'7" POOL AND 8'6"X13'7" SPA PER STD PLN # 265 - 1 OF 2
Permit Issued
Issued on 9/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 MARVEL DELACRUZ
Corrections Issued 3/14/2020 MARVEL DELACRUZ
Quality Review Completed 3/16/2020 GUANG MIN TUNG
Building Plans Picked Up 3/25/2020 APPLICANT
Applicant returned to address corrections 6/24/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/14/2020 MARVEL DELACRUZ
Applicant returned to address corrections 8/3/2020 MARVEL DELACRUZ
Plan Check Approved 8/25/2020 MARVEL DELACRUZ
Issued 9/3/2020 APPLICANT
CofO in Progress 6/25/2021 ARAM AVEDISIAN
CofO Issued 8/28/2021 MICHAEL SMITH
Permit Finaled 8/28/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/14/2020 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/15/2020 Corrections Issued ARAM AVEDISIAN
Pre-Gunite 10/5/2020 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/8/2020 Approved ARAM AVEDISIAN
Grounding or Bonding 10/8/2020 Partial Approval ARAM AVEDISIAN
Pool Piping 10/8/2020 Approved ARAM AVEDISIAN
Pre-Gunite 10/8/2020 Approved ARAM AVEDISIAN
Enclosure/Fence 3/1/2021 Corrections Issued ARAM AVEDISIAN
Enclosure/Fence 3/4/2021 Approved ARAM AVEDISIAN
Pool Equipment Noise Test 3/24/2021 Approved FELIPE PENICHE
Final 4/12/2021 Corrections Issued MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Not Ready MICHAEL TEMPLE
Final 5/17/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Not Ready JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Not Ready ARAM AVEDISIAN
Final 6/10/2021 Not Ready for Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved RONALD COWAN
Final 6/16/2021 Corrections Issued ARAM AVEDISIAN
Final 6/22/2021 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 6/22/2021 Approved ARAM AVEDISIAN
Final 6/25/2021 OK to Issue CofO ARAM AVEDISIAN