3509 N LAURELVALE DR 91604
Certificate Information: 3509 N LAURELVALE DR 91604
- Application / Permit
- 20047-20000-00255
- Plan Check / Job No.
- B20VN03069
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 11'0X 13'7" POOL AND 8'6"X13'7" SPA PER STD PLN # 265 - 1 OF 2
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | MARVEL DELACRUZ |
| Corrections Issued | 3/14/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 3/16/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/25/2020 | APPLICANT |
| Applicant returned to address corrections | 6/24/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/14/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/3/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 8/25/2020 | MARVEL DELACRUZ |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 6/25/2021 | ARAM AVEDISIAN |
| CofO Issued | 8/28/2021 | MICHAEL SMITH |
| Permit Finaled | 8/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2020 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/15/2020 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Gunite | 10/5/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 10/8/2020 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 10/8/2020 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 10/8/2020 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 3/1/2021 | Corrections Issued | ARAM AVEDISIAN |
| Enclosure/Fence | 3/4/2021 | Approved | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 3/24/2021 | Approved | FELIPE PENICHE |
| Final | 4/12/2021 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| Final | 5/17/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/17/2021 | SGSOV Not Ready | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 6/10/2021 | Not Ready for Inspection | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | RONALD COWAN |
| Final | 6/16/2021 | Corrections Issued | ARAM AVEDISIAN |
| Final | 6/22/2021 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 6/22/2021 | Approved | ARAM AVEDISIAN |
| Final | 6/25/2021 | OK to Issue CofO | ARAM AVEDISIAN |