3771 S MAY ST 90066
Certificate Information: 3771 S MAY ST 90066
- Application / Permit
- 20047-20000-00225
- Plan Check / Job No.
- B20VN02729
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool with spa per city standard plan #268. See comments.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | ANGELICA DAVE |
| Plan Check Approved | 2/20/2020 | ANGELICA MARTINEZ |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 9/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/24/2022 | DANIEL ORRANTE |
| CofO Issued | 9/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/18/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 2/18/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Custom Derian Pools; Lic. No.: 977981-C53 | P O BOX 1352 MOORPARK, CA 93020 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Grounding or Bonding | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Pool Piping | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Pre-Gunite | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Rough-Electrical | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Rough-Plumbing | 3/2/2020 | Approved | JOHNNY MIRANDA |
| Deputy Shotcrete | 3/11/2020 | Conditional Approval | JOHNNY MIRANDA |
| Deck | 3/23/2020 | Approved | DAVID FEILER |
| Enclosure/Fence | 9/8/2020 | Approved | JOHNNY MIRANDA |
| Equipment Noise Level | 9/23/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Pool Equipment Noise Test | 9/29/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Pool Equipment Noise Test | 9/30/2020 | Approved | STEVEN BELTRAN |
| ELECTRICAL-Final | 10/2/2020 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Approved | ENRIQUE MIRELES |
| Final | 10/2/2020 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 10/2/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/2/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 10/7/2020 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 9/24/2022 | OK to Issue CofO | DANIEL ORRANTE |